NEW QUESTION 54
In which master data object do you set the standard values for an operation?
- A. Production Resource/Tool (PRT)
- B. Material Master
- C. Routing
- D. Work Center
Answer: C
NEW QUESTION 55
What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
- A. ATP checks can be adjusted to also consider future requirements and receipts.
- B. ATP checks can be carried out automatically when releasing a production order.
- C. ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
- D. ATP checks are used to evaluate the free capacity on a certain work center.
- E. ATP checks are mandatory for lead-time scheduling.
Answer: A,B
NEW QUESTION 56
Which of the following situations occur when a production order is set to Technically Complete (TECO)?
(Choose three.)
- A. Reservations are deleted.
- B. The order and its operations receive the system status Locked (LKD).
- C. Capacity requirements are deleted.
- D. Purchase orders for external operations or non-stock materials are deleted.
- E. The order is no longer relevant for Material Requirements Planning.
Answer: A,C,E
NEW QUESTION 57
When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.
What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?
- A. Activate requirements planning in Customizing for MRP areas in plant 1000 and specify the plant parameters for plant 1000 in the MRP views in material master.
- B. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in Customizing.
- C. Set up the planning files in Customizing and specify the plant parameters for plant 1000 in Customizing of the MRP group.
- D. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in the MRP views in material master.
Answer: B
NEW QUESTION 58
During the processing of production orders planned and actual costs are determined.
On which of the following objects can you collect these costs? (Choose two)
- A. Planned order
- B. Product cost collector
- C. Production order
- D. Work center
Answer: B,C
NEW QUESTION 59
The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order.
However, a corresponding rescheduling exception message does not appear.
What could be the reasons? (Choose two)
- A. Requirements planning has not been carried out.
- B. The delta between the availability dates falls within the tolerance window defined in Customizing.
- C. The MRP elements are linked via fixed pegging.
- D. The fixed planned order is outside the rescheduling horizon.
Answer: B,D
NEW QUESTION 60
Which of the following features are offered by MRP areas in SAP ECC? (Choose two)
- A. Subcontracting is supported by MRP areas.
- B. Make-to-order production is supported by storage location MRP areas.
- C. An MRP area may include different storage locations.
- D. A storage location may be assigned to different MRP areas.
Answer: A,C
NEW QUESTION 61
Which of the following functions does SAP Supply Chain Management (SCM) offer?
- A. Optimization of the procurement strategy with the supplier pool
- B. Planning of supply chains across company boundaries
- C. Product development, safety, quality, and maintenance
- D. Communication with customers through different interaction channels
Answer: B
NEW QUESTION 62
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
- A. Requirements planning creates an appropriate exception message in basic dates scheduling.
- B. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
- C. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
- D. Lead time scheduling cannot take place.
Answer: B
NEW QUESTION 63
From what point can you no longer use the Read PP master data in the production order?
- A. After the first posting of goods movements or confirmation.
- B. After printing the order papers.
- C. After assigning the confirmed quantity of a material component due to carrying out a material availability check.
- D. From the release of the production order.
Answer: A
NEW QUESTION 64
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)
- A. A planning scenario must be released to use it in long-term planning.
- B. Reorder point planned materials can be included in long-term planning.
- C. In case of external procurement, long-term planning creates purchase requisitions.
- D. Long-term planning generally is operational planning of important components.
Answer: A,B
NEW QUESTION 65
Which option for selecting a routing exists when you create a production order?
- A. Automatic selection based on the selection ID in the material master
- B. Automatic selection of a reference operation set
- C. Manual selection based on the list of routings maintained in the material master
- D. Manual selection based on settings in the order type-dependent parameters
Answer: D
NEW QUESTION 66
The availability check during production order creation should use a different scope of check than during order release.
How can you fulfill this requirement?
- A. Maintain appropriate checking rules in checking control for order creation and order release.
- B. Maintain appropriate availability checking rules in the order type-dependent parameters.
- C. Maintain appropriate availability checking rules in the production scheduling profile.
- D. Maintain an appropriate availability checking group in the material master.
Answer: A
NEW QUESTION 67
After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).
Which of the following planning file entries for this material are set by the system?
- A. The BOM explosion, the NETCH, and the NETPL planning indicators
- B. The BOM explosion and the NETPL planning indicator
- C. The NETCH and NETPL planning indicators
- D. The BOM explosion indicator
Answer: A
NEW QUESTION 68
What sequence do you follow in master data maintenance to define the production of a material?
- A. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
- B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
- C. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
- D. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
Answer: D
NEW QUESTION 69
......
SAP C-TSCM42-67 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Process Orders (PP-PI) < 8% | Identify specific properties of process orders. |
| Basics on SAP Business Processes (E-Learnings) < 8% | Outline the scope of SAP SCM business processes. |
| Lean Manufacturing (PP-REM, PP-KAB) 8% - 12% | Outline the highlights of repetitive manufacturing and kanban. |
| Production Orders Basics (PP-SFC) 8% - 12% | Apply production order functionality. |
| Material Requirements Planning (PP-MRP) > 12% | Explore material requirements planning functions. |
| Master Data (LDM) 8% - 12% | Set up master data for production planning and manufacturing. |
Updated C-TSCM42-67 Exam Practice Test Questions: https://www.bootcamppdf.com/C-TSCM42-67_exam-dumps.html