NEW QUESTION 72
What is the function of the offset within a maintenance strategy? choose 1 answer
- A. it determine the first due date of the maintenance package
- B. it shift the next planned date due to the delay of the confirmation
- C. it sets the start date of the maintenance plan
- D. it extends the cycle length of a maintenance package
Answer: A
NEW QUESTION 73
Which of the following statements about commitments management are correct?
- A. Commitments are used to update and monitor resources that are required for external procurement.
- B. Commitment data is built up when the scheduled order resources are valuated.
- C. Commitment values can exceed planned costs.
- D. Commitments are contractual obligations that are entered in accounting.
- E. Commitments lead to actual costs as a result of various business transactions.
Answer: A,B,C,E
NEW QUESTION 74
what must you define for the material master before you can refurish the corresponding material? choose 1 answer
- A. MRP type replenishement
- B. transport group 0001
- C. split valuation of stocks
- D. serail number profile
Answer: C
NEW QUESTION 75
Which must you define before you can create a new function location? choose 2 answers
- A. functional location category
- B. reference functional location
- C. structure indicator
- D. status profile
Answer: A,C
NEW QUESTION 76
Which of the following is true about settlement rules?
- A. It can be changed when the first settlement rule is maintained for the order.
- B. It must be entered manually in the order.
- C. It cannot be changed once it is determined.
- D. The account assignment object is proposed from the master record for thereference object.
Answer: A,D
NEW QUESTION 77
Why do you create maintenance planner group? choose 1 answer
- A. to map a group of persons responsible for maintenance plans
- B. to map a group of persons which plan maintenance budgets
- C. to map a group of persons which plans maintenance activities for technical objects
- D. to map a group of persons responsible for maintenance strategies
Answer: C
NEW QUESTION 78
To which objects can you assign a budget? choose 2 answers
- A. WBS element
- B. maintenance order
- C. functional location
- D. planning plant
Answer: A,B
NEW QUESTION 79
Which operation can the responsible person perform after a maintenance order in technically completed?
choose 3 answers
- A. update the estimated cost
- B. lock or unlock the order
- C. change the planned cost
- D. create invoice receipt for delivered materials
- E. change the settlement rule An internal server error occurred.